Fictional sample

All projects, companies, people and numbers in this scenario are fictional. They illustrate the review deliverable and do not come from real client materials.

Northstar Auto Parts and Horizon Information are invented scenario names.

Pascal Yin · WMS / LES implementation

Pre-go-live plan review · Sample

Before signing a contract, freezing a blueprint or fixing a go-live date, identify implementation arrangements that remain unresolved. Every finding explains how it was identified.

Fictional project
Northstar Auto Parts · Plant 2 WMS / LES implementation
Materials reviewed
Horizon Information's fictional implementation plan rev.B and project schedule, §1–§5
Review date
2026-10-06
Reviewer
Pascal · WMS / LES programme manager in large-scale manufacturing

One-page conclusion

We do not recommend signing this plan as it stands.

The problem is not that the supplier is bound to do a poor job. It is that several key arrangements in the plan are still unsettled: the scope has no stated assumptions, so every change will be argued one by one; the blueprint covers only normal flows; data preparation hands the equipment fields to people who cannot fill them in; and interfaces, cutover and acceptance are not written down to a level that can be checked. These are the most expensive sources of rework after go-live.

12
High risk: must be closed before signing
8
Medium risk: write into the contract or the go-live plan
5
Documents the supplier must complete before signing
18
Follow-up questions you can send straight to the supplier

Before signing, make the supplier answer these 5 things first

  1. 1
    Add an assumptions section to the charter: response deadline, authorized signatories, data responsibility, change process.Out-of-scope requests have nothing to be checked against today; every addition has to be argued again.→ A1
  2. 2
    Write the three black-box scheduling clauses into the contract: location-level data return, lead time and price for rule changes, rule documentation delivered with the system.Once the final payment is made, these can only be bought.→ A3
  3. 3
    Add reverse flows to the blueprint: rollback, cancellation, returns, task cancellation, equipment exceptions, each written down to the role.Outside the 4 main flows, the system currently has no path.→ B1
  4. 4
    Split the location table in two by who holds the information; replace "in progress" on item coding with three sample checks.Until these two are settled, the go-live date is hanging in the air.→ C1, C2
  5. 5
    Provide a posting-scenario list for the interfaces, reversals included, and write cutover prerequisites and rollback conditions into the go-live plan.These two are where things most often blow up on go-live day.→ D1, D2

1. Implementation plan and go-live readiness

Every finding is checked item by item against the pitfall rules and the WMS / LES go-live checklist: whether the plan says it, how far it goes, and who owns it. Each finding states three things: what the plan cannot yet claim, what to get from the supplier, and what counts as closed. The method notes give the rule number, what was looked at, the method used and what it cannot prove; the decision thresholds are not published.

A. Scope and contract

3 selected
A1High riskExperience-based judgment · Pitfall L1

The charter has no assumptions section: every added requirement reopens the argument over whether it is a change

Plan excerpt
§1 Scope: implement per the attached feature list; duration 6 months; 1,240 person-days in total.
Cannot be claimed yet
That scope and duration are fixed. Response deadlines, signatories and data ownership are not written down as assumptions; once an assumption changes, nobody owns the extra person-days and time.
Get from the supplier
Add an assumptions section to the charter: the business side replies within an agreed number of working days, and no reply by the deadline counts as confirmation; the signatories and authorized persons; the business side is responsible for source data; out-of-scope requests go through change control. Have contract wording checked in the relevant jurisdiction.
What counts as closed
The section is in the charter and both parties have signed.
How this finding was found
What was looked at
§1 Scope and duration
Method
Checked against pitfall L1, the eight things to pin down at initiation: does the charter have assumptions, and does it have a change-control clause.
Rule number
SCP-01 Missing assumptions
What it cannot prove
It cannot prove the project will overrun; it only proves there is nothing to check against when a scope dispute arises.
A2Medium riskExperience-based judgment · Pitfall L1

The 86 functions are not marked standard or custom: nobody can say how the 1,240 person-days were estimated

Plan excerpt
§1 Attached feature list: 86 items, 1,240 person-days in total.
Cannot be claimed yet
That the effort was broken down by function. Standard functions mostly cost configuration and implementation days; only custom ones consume development days. Without the marking, there is no footing for later change talks or effort checks.
Get from the supplier
Add a standard / custom column to every row of the feature list. For custom rows, attach the development manager's effort split by frontend, backend and interface, and enter them in the customization register.
What counts as closed
Every row is marked, and every custom item has a number, a requester and an effort split.
How this finding was found
What was looked at
Attached feature list (86 rows)
Method
Read row by row: is standard separated from custom, and does each custom row have its own effort basis.
Rule number
SCP-02 Standard/custom not marked
What it cannot prove
It cannot prove the estimate is too high; it only proves it cannot be checked today.
A3High riskExperience-based judgment · Pitfall L2

ASRS scheduling is a black box, and the contract has no data return, no price for rule changes and no rule documentation

Plan excerpt
§1 ASRS scheduling is the equipment integrator's responsibility; WMS sends tasks down to the storage area.
Cannot be claimed yet
That after acceptance the factory can see location-level stock for itself and control the rules itself. Today WMS records only down to the area, the location-level book is in the integrator's hands, and neither how long a rule change takes nor what it costs is written anywhere.
Get from the supplier
Add three clauses to the contract: return of location-level stock and task status; lead time and charge for changing a rule; rule list, parameter tables and configuration documents delivered with the system.
What counts as closed
All three are in the contract or an addendum, and final payment is tied to them.
How this finding was found
What was looked at
The one sentence on system boundary in §1; the deliverables list in the draft contract
Method
Checked against pitfall L2, black box or white box: the three clauses a black-box solution must have in the contract before final payment, one by one.
Rule number
CTR-01 Three black-box clauses
What it cannot prove
It cannot prove the integrator will be uncooperative; it only proves the factory has no say after acceptance.

B. Blueprint and requirements

2 selected
B1High riskExperience-based judgment · Pitfall L1b

The blueprint draws only 4 normal flows: not one cancellation, rollback or return

Plan excerpt
§2 Blueprint draft: 4 main flows, namely inbound, outbound, delivery and stocktake.
Cannot be claimed yet
That the blueprint is complete. Reverse flows come up only a few times a week, so nobody volunteers them during interviews; when they come up after go-live the system has no path, and the only option is asking IT to edit the data.
Get from the supplier
Add a chapter on reverse flows: receipt rollback, putaway cancellation, wave cancellation, short and over picks, return of over-shipments, purchase returns, task cancellation and equipment exceptions. Draw each one in the same format as the normal flows, down to the role.
What counts as closed
Every reverse flow has a diagram and roles, and goes through final review together with the main flows.
How this finding was found
What was looked at
Feature list and flow diagrams in the §2 blueprint draft
Method
Searched the feature list for cancel, rollback and return, then checked item by item against the pitfall L1b reverse-flow list.
Rule number
BLP-01 Reverse flows missing
What it cannot prove
It cannot prove these cases will happen; it only proves there is no path when they do.
B2Medium riskExperience-based judgment · Pitfall L3

Requirement changes are "implemented after development assessment": the project manager is bypassed

Plan excerpt
§2 Requirement changes: raised by the business side, implemented after assessment by development.
Cannot be claimed yet
That effort and milestones are under control. Requests go straight to development with no assessment, no scheduling and no record; each looks small, but enough of them make the effort sheet wrong.
Get from the supplier
Every new request during development goes to the project manager first: accept or not, change or not, where it slots in, what it pushes out. Line-down emergencies may be fixed first and registered afterwards.
What counts as closed
The change process names the project manager as the entry point, and there is a request register.
How this finding was found
What was looked at
The one sentence on requirement changes in §2
Method
Checked against pitfall L3, requirements and effort: is the project manager the entry point, and is there an assessment and scheduling step.
Rule number
REQ-01 Request entry point
What it cannot prove
It cannot prove scope creep will happen; it only proves nobody stops it when it does.

C. Data preparation

2 selected
C1High riskExperience-based judgment · Pitfall L6 / Checklist F1, F3, F5

"The customer supplies location master data on our template": the customer cannot fill in the 8 ASRS columns

Plan excerpt
§3 The customer supplies material and location master data on our template (one table).
Cannot be claimed yet
That location data will be collected in one round. Aisle, single or double depth, near and far end, linked locations, and putaway and picking route sequence come from the equipment layout drawings and the scheduler configuration; only the equipment supplier has them. The table comes back looking full, yet those columns are empty from top to bottom.
Get from the supplier
Split the table in two by who holds the information, a business table and an equipment table; settle the location coding rule first; when the tables come back, count the fill rate column by column.
What counts as closed
The equipment supplier provides the equipment table, it is merged with the business table by location code, and every wholly empty column is confirmed one by one.
How this finding was found
What was looked at
§3 Data preparation: one location table given to the customer to fill in
Method
Checked against pitfall L6 and checklist items F1, F3 and F5: who holds each field; flagged wherever the person filling in is not the source of the information.
Rule number
DAT-01 Field source
What it cannot prove
It cannot prove this customer is unable to fill it in; it only proves the template is not split by source.
C2High riskExperience-based judgment · Pitfall L15

Item coding is "in progress", and the go-live date is already fixed

Plan excerpt
§3 Item coding: the customer's data-governance project is in progress and will finish before go-live.
Cannot be claimed yet
That the codes will be clean at go-live. "In progress" has no scope and no acceptance method; with the date fixed, code cleanup gets pushed past go-live, and it cannot be done after go-live.
Get from the supplier
Replace "in progress" with three checks: sample 100 materials at random, with zero cases of the same physical item named differently across purchasing, warehouse and production; reused old codes cleared out; unit-conversion rules entered in the system.
What counts as closed
The three check results are in before the go-live date is set.
How this finding was found
What was looked at
The one sentence on item coding in §3; the go-live date in §5
Method
Checked against pitfall L15, the three go-live questions: does coding have a checkable criterion, and was the date set before the check.
Rule number
DAT-02 Coding criterion
What it cannot prove
It cannot prove the codes are dirty today; it only proves nobody can tell today.

D. Interfaces, go-live and acceptance

3 selected
D1High riskExperience-based judgment · Pitfall L13 / Checklist J3

"Standard ERP interface, 2 weeks of integration testing": no posting scenarios listed, reversals not mentioned

Plan excerpt
§4 WMS connects to the customer's ERP through the standard interface; integration testing takes 2 weeks.
Cannot be claimed yet
That 2 weeks is enough. ERP is the widest interface of all: purchase receipts and returns, transfers, material issues, stocktakes, line-side returns and more, a dozen-plus posting scenarios, each needing its reversal confirmed separately. Testing the forward posting but not the reversal is the number-one reason the books do not match after go-live.
Get from the supplier
A posting-scenario list, each type marked for whether it includes a reversal, used as the acceptance basis for completing integration testing.
What counts as closed
Every type of reversal has been run through integration testing once, with records.
How this finding was found
What was looked at
The one sentence in the §4 integration-test plan
Method
Checked against pitfall L13 and checklist item J3: are posting scenarios listed, and do they include reversals.
Rule number
ITF-01 Reversals
What it cannot prove
It cannot prove 2 weeks is too short; it only proves no scenarios are listed, so nobody can judge.
D2High riskExperience-based judgment · Pitfall L15 / Checklist K1–K5, L2

"One-shot weekend cutover": no rollback conditions and no cutover prerequisites

Plan excerpt
§5 Go-live plan: one-shot cutover over a weekend.
Cannot be claimed yet
That a weekend cutover is safe. All five prerequisites must be met before cutting over: upstream and downstream systems go live together, the opening stocktake is done, purchasing and transfer data are in place, the work-order, quality and posting chains all run end to end, and automation equipment has passed integration testing.
Get from the supplier
Write down the rollback triggers, the rollback time window, and the point past which the only way is forward.
What counts as closed
The go-live plan contains the prerequisite checklist and a rollback plan, ticked off item by item one week before go-live.
How this finding was found
What was looked at
The cutover approach in the §5 go-live plan
Method
Checked against checklist items K1–K5 and L2: is each prerequisite written down, and do rollback conditions exist.
Rule number
GOL-01 Rollback
What it cannot prove
It cannot prove the cutover will fail; it only proves there is no way back if something goes wrong.
D3Medium riskExperience-based judgment · Pitfall L17

Acceptance is "after 3 months of stable operation": none of the 5 measures has a threshold

Plan excerpt
§5 Acceptance: after the system has run stably for 3 months.
Cannot be claimed yet
That acceptance will go smoothly after 3 months. If thresholds are not set at initiation, at acceptance every party counts in the way that favours itself; issue closure rate and functional completion rate are argued over most.
Get from the supplier
Write thresholds for the 5 measures into the initiation document: document and delivery accuracy, system availability, outbound efficiency or cycle-time attainment, issue-list closure rate and functional completion rate, together with the definitions of what counts as an issue and what counts as a confirmed function.
What counts as closed
Thresholds and definitions are in the initiation document, signed by all three parties.
How this finding was found
What was looked at
The acceptance clause in §5
Method
Checked against pitfall L17, trial operation and acceptance: do the 5 measures have thresholds, and are the definitions written down.
Rule number
ACC-01 Acceptance thresholds
What it cannot prove
It cannot prove acceptance will drag on; it only proves there will be nothing to check against when the time comes.

Review boundaries

  • Only the text of the plan and the project schedule was read; the site and the system were not seen.
  • The review covers WMS / LES implementation and project management: scope, contract, blueprint, requirements, data, interfaces, go-live and acceptance. It does not assess equipment selection or recalculate mechanical capacity.
  • Everything here is experience-based judgment against the pitfall library and the go-live checklist, each finding marked with its rule number. No overall score, no probabilities.
  • This sample shows 10 selected findings; the full sample has 20.